A complete bathroom renovation with reinforced walls, modern lighting, a professionally installed vanity unit, and improved ventilation. Structural enhancements and smart design solutions ensure durability, comfort, and long-term functionality.

Execution Time: 3 weeks
Completed Tasks:
  • Reinforced weak walls with additional studs and installed wall insulation.
  • Installed a vanity unit with a professionally joined worktop, coordinated by a skilled carpenter.
  • Replaced the ceiling and fitted modern spotlights for enhanced lighting.
  • Plastered the walls, with tiling primarily around the bath area.
  • Installed a new extractor fan and wired it with a timer for improved ventilation.
Project Challenges:
  • Weak walls required reinforcement to ensure stability and durability.
  • Precise carpentry work was necessary to properly integrate the vanity unit and worktop.
  • The bathroom lacked an extractor fan, making ventilation a key priority.
Final Outcome:

A well-structured and modernized bathroom with reinforced walls, enhanced lighting, and improved ventilation. The professionally installed vanity unit and new ceiling contribute to a stylish and functional space designed for long-term comfort and durability.